PZG — FY2026 Financial Report Analysis
Full Year · Fiscal year 2026 · Published Sep 18, 2026 by Claude
Paramount Gold Nevada closed FY2026 with cash up from $1.35m to $9.93m after an ATM raise that cleared at roughly $1.58 a share versus $0.50 the year before, won the federal Record of Decision for Grassy Mountain, and still carries a going-concern warning with runway management puts at about March 2027.
Overview: a permitting milestone year, funded by a share price that finally cooperated
Paramount Gold Nevada (NYSE American: PZG) has no mine, no revenue and no production. It owns two gold projects in the western US — Grassy Mountain in Malheur County, Oregon (an underground deposit with proven and probable reserves, in the final stage of permitting) and Sleeper, 26 miles northwest of Winnemucca, Nevada (a past-producing open pit the company is studying for restart). Its fiscal 2026 year ended June 30, 2026, and the 10-K was filed September 17, 2026.
For a company like this, the income statement is not the scoreboard. There is nothing to sell, so every dollar spent shows up as a loss. What actually matters is: how much cash is in the bank, how fast it is leaving, how many permits and studies got finished with it, and how much ownership existing shareholders gave up to pay for it. On that scoring, FY2026 was the strongest year Paramount has had in some time — and the reason is largely that the stock traded between $1.04 and $2.71 in the back half of the year versus $0.31–$0.65 across all of FY2025, which let the company sell far fewer shares for far more money.
Key figures
| Metric | FY2026 (yr. ended 6/30/26) | FY2025 (yr. ended 6/30/25) | YoY change |
|---|---|---|---|
| Revenue | $0 | $0 | n/a (pre-production) |
| Cash and cash equivalents (period end) | $9,931,206 | $1,351,001 | +635% |
| Total operating expenses | $8,331,756 | $6,955,519 | +19.8% |
| Exploration and development expense | $3,567,816 | $2,603,457 | +37.0% |
| Net loss | $15,560,223 | $9,050,423 | +71.9% |
| — of which non-cash fair-value losses | $5,702,194 | $435,824 | +1,209% |
| Loss per share (basic and diluted) | $(0.19) | $(0.13) | +46.2% |
| Cash used in operating activities | $7,283,822 | $6,267,284 | +16.2% |
| Cash from financing activities | $15,914,027 | $2,356,709 | +575% |
| Shares issued and outstanding | 86,124,381 | 75,420,743 | +14.2% |
| Grassy Mountain proven + probable gold reserves | 405,000 oz | 380,000 oz | +6.6% |
| Total liabilities | $26,920,570 | $18,834,909 | +42.9% |
The net loss nearly doubled, but four-fifths of that has nothing to do with spending
Net loss went from $9.05m to $15.56m, an increase of $6.51m. Operating expenses only rose $1.38m of that. The other $5.27m is the year-over-year swing in two non-cash mark-to-market charges — accounting adjustments that revalue liabilities Paramount carries at fair value, with no cash changing hands:
- $4,868,289 loss from the change in fair value of the derivative embedded in the Sprott royalty convertible debenture (versus $435,824 in FY2025). The filing is specific about the driver: the estimated "cumulative present value of royalty stream" that Sprott could convert into rose from $16,758,545 to $24,750,334 as gold and silver prices appreciated. Paramount also switched the valuation method from Black-Scholes to a Monte Carlo simulation during the year, explicitly "because appreciation in gold and silver prices have caused the Company's buyback provision to become economically substantive" and a simple option formula could not capture the interaction between the conversion and buyback features.
- $833,905 loss from the change in fair value of the warrant liability. In August 2025 Paramount sold 2,941,176 pre-funded warrants (warrants already paid for, exercisable at $0.0001) for $2,000,000 — about $0.68 per underlying share. Because these are classified as a liability rather than equity, they get re-valued against the share price each period end. The stock went up, so the liability went up, so the company books a loss. Shareholders were not worse off; the accounting simply follows the share price.
Strip both out and FY2026's pre-tax loss is roughly $9.85m against $8.60m in FY2025 — a real increase, but an ordinary one.
The paradox worth naming: the two biggest line items dragging the reported loss lower are direct consequences of good news. Higher gold prices made Sprott's royalty option more valuable, and a higher share price made the pre-funded warrants more valuable. Both make the income statement look worse.
Takeaway: FY2026 bought Paramount the two things a pre-production developer needs most — a federal Record of Decision at Grassy Mountain and a cash balance that went from $1.35m to $9.93m — at a cost of only 14% share dilution, because the stock re-rated before the raise rather than after. But the company still says its cash only funds operations to roughly March 2027, still carries a going-concern warning, and still needs ~$190m of initial capital it does not have. Management converted a weak balance sheet into permits and studies; it has not yet converted permits into financing for construction.
Where the operating money went
Total expenses of $8.33m break down as follows, and the movements are explained specifically in the MD&A rather than left vague:
| Expense | FY2026 | FY2025 | Change | What the filing attributes it to |
|---|---|---|---|---|
| Exploration and development | $3,567,816 | $2,603,457 | +37.0% | Permitting work at Grassy Mountain ($3,132,602 of the total); Sleeper accounted for $435,214, up from $264,174, mostly the Initial Assessment |
| Land holding costs | $764,607 | $743,119 | +2.9% | Claim maintenance fees; increase described as normal inflation, not significant |
| Reclamation (Sleeper) | $171,909 | $200,950 | −14.4% | Streamlined monitoring and compliance activities |
| Salaries and benefits | $1,355,560 | $1,640,394 | −17.4% | Lower salary and stock-based compensation on reduced headcount, partly offset by higher short-term incentives. Non-cash stock comp inside this line fell to $265,952 from $387,052 |
| Directors' compensation | $276,764 | $320,848 | −13.7% | Lower equity-based compensation |
| Professional fees | $745,287 | $446,723 | +66.8% | Higher audit and quarterly review fees, more legal expense on corporate activities, higher advisory fees |
| General and administrative | $1,222,166 | $774,615 | +57.8% | Higher investor relations and stock exchange listing costs, plus broad-based increases |
| Accretion (reclamation obligation) | $227,647 | $225,413 | +1.0% | Non-cash unwinding of the discount on the Sleeper reclamation liability |
The shape of this is what you want from a developer in a permitting year: project spend up 37% while payroll came down 17%. The uncomfortable counterpoint is the corporate overhead line — professional fees and G&A together rose $746,115, or 61%, which is almost as much as the entire increase in project spending ($964,359). Investor relations, listing costs and advisory fees are what a company spends on when it is raising money and marketing a re-rating; they are real cash out the door, and they are not permits.
Cash used in operations was $7,283,822, up 16.2%, or roughly $607,000 per month. That is the number to hold against the cash balance.
The balance sheet: the same raise, on much better terms
Paramount funded FY2026 almost entirely through its at-the-market ("ATM") equity program with Cantor Fitzgerald and A.G.P./Alliance Global Partners — a facility that lets the company dribble shares into the open market at prevailing prices rather than negotiate a discounted block deal.
| ATM issuance | FY2026 | FY2025 |
|---|---|---|
| Shares issued | 8,785,663 | 4,728,165 |
| Net proceeds | $13,914,027 | $2,356,709 |
| Implied net price per share | ~$1.58 | ~$0.50 |
1.86x the shares raised 5.9x the money. That is the single most consequential financial fact of the year, and it is entirely a function of when the selling happened relative to the share price. Add the $2,000,000 pre-funded warrant placement in August 2025 and total financing inflow was $15,914,027 against $7.33m of cash burn, leaving cash at $9,931,206 versus $1,351,001 a year earlier.
Total dilution was 10,703,638 shares (+14.2%), of which 8,785,663 came from the ATM; the balance is mostly shares issued to pay debenture interest (see below) plus restricted stock. Remaining option and restricted-share-unit overhang is negligible — 50,000 options at a $0.60 strike and 844,400 restricted share units. The real forward dilution sources are the untriggered 2,941,176 pre-funded warrants, continued ATM use, and quarterly interest paid in stock.
Working capital, which management calculates excluding the $2,833,905 warrant liability (reasonable, since that liability is settled by delivering shares, not cash), was approximately $10,376,448. On a strict GAAP basis current assets less current liabilities is $7,542,543.
The Sprott debenture: a $15m debt that is probably becoming a royalty
This is the most important structural feature of Paramount's capital stack and the easiest thing to misread from the balance sheet.
In December 2023 Paramount took $15,000,000 from Sprott Private Resource Streaming and Royalty as a secured royalty convertible debenture. It pays 10% interest annually, which Paramount elects to settle in shares at a 7% discount to the 10-day volume-weighted average price — $1,520,833 of the $1,694,855 FY2026 interest expense was paid in stock, not cash (the remaining $174,022 is amortization of issuance costs). At Sprott's sole discretion, the debenture can be repaid in cash or converted into a 4.75% gross revenue royalty on gold and silver produced at Grassy Mountain, at the earlier of commercial production or the fifth anniversary — December 2028. It is secured by deeds of trust over both Grassy Mountain and Sleeper.
The debenture shows up in three places totalling more than its face value: $11,804,567 of debt liability (the $12,239,622 host contract less $435,055 unamortized issuance costs), plus $8,946,218 of derivative liability for the conversion and buyback features. That $8.95m derivative is not a separate debt — it is the accounting estimate of how much the royalty option is worth to Sprott.
And that estimate carries the signal. With the present value of the royalty stream now marked at $24.75m against a $15m conversion threshold, Sprott converting rather than asking for cash back is the economically obvious path. The practical read: Paramount most likely will not have to find $15m of cash in December 2028 — but Grassy Mountain will carry a 4.75% gross revenue royalty for life of mine, on top of the existing third-party royalties on both properties (a 2% net smelter return to Franco-Nevada on 2,474 Sleeper claims, 1% to the Snyder Syndicate on the 1,044 Sleeper Gold mine claims, and a 2–4% net smelter return owed by lessee Calico on the Cryla claims). Paramount retains a buyback option on half the royalty for $11.25m at the second anniversary or $12.375m at the third — which is exactly the provision the company says became "economically substantive" this year, and the reason it had to move to a Monte Carlo model. Paramount was in compliance with the debenture's positive-cash and positive-adjusted-working-capital covenants at June 30, 2026.
Grassy Mountain: the federal approval is done, the state package is in its final stages
This is where the year's project spending went, and the milestones are dated and concrete:
- July 23, 2025 — Malheur County approved a two-year extension of the Conditional Use Permit and Sage Grouse Permit.
- December 2025 — Oregon issued the Draft Consolidated Permit Package, the first time in the state's history a mining project has advanced through Oregon's consolidated permitting framework. Public consultation has since closed.
- January 29, 2026 — the Bureau of Land Management issued the Record of Decision and Final Environmental Impact Statement, completing federal environmental review under the National Environmental Policy Act and approving the project's federal Plan of Operations.
- May 2026 — an updated Feasibility Study (S-K 1300 compliant, prepared by Ausenco, effective May 27, 2026) replacing the 2022 study with current metal prices, capital and operating cost estimates, and a revised mine plan.
The updated feasibility economics, as filed:
| Grassy Mountain feasibility study | Figure |
|---|---|
| Gold price assumption / silver price assumption | $3,600/oz / $48.00/oz |
| Mine life | 9.3 years |
| Mining method | Underground mechanized cut-and-fill, decline access, 750 short tons/day plant |
| Recovered gold (life of mine) | 385,800 oz (avg. 41,400 oz/yr) |
| Recovered silver (life of mine) | 480,100 oz (avg. 51,500 oz/yr) |
| Gold recovery rate | 92.6% |
| Cash costs, net of by-products | $1,217.95/oz Au |
| All-in sustaining cost, net of by-products | $1,441.57/oz Au |
| Initial capital | $189.8m |
| Sustaining capital / closure | $65.1m / $21.1m |
| Post-tax NPV at 5% / IRR / payback | $374.7m / 38.9% / 2.2 years |
| Pre-tax NPV at 5% / IRR / payback | $458.9m / 42.8% / 2.1 years |
Two caveats a reader should apply to those returns. First, the $3,600/oz gold price assumption is doing a lot of work — at an all-in sustaining cost of $1,442/oz the study is modelling a margin of over $2,150/oz, so the headline 38.9% post-tax internal rate of return (the annualized return the project earns on the capital put into it) is highly sensitive to the gold price holding up. Second, $189.8m of initial capital is roughly 19x Paramount's year-end cash balance. A strong feasibility study is a precondition for financing construction, not a substitute for it, and nothing in this filing indicates that financing is arranged.
Reserves rose to 405,000 oz of gold (2,207,000 short tons at 0.184 oz/st) plus 625,000 oz of silver, from 380,000 oz a year earlier. Note the composition: tonnage rose 15.4% while grade fell from 0.200 to 0.184 oz/st. That is the signature of a higher metal price lowering the economic cut-off grade — the reserve cut-off in the new study uses $2,750/oz gold and a net-smelter-return cut-off of $200.64 per ore ton. More ounces, but lower-grade ones pulled in by price rather than found by drilling. Grassy Mountain's net book value at June 30, 2026 was approximately $23.4m.
Sleeper: an Initial Assessment that reframes an old mine as a heap-leach restart
Sleeper is a historic open pit mined by AMAX Gold from 1986 to 1996, which produced 1.66m oz of gold and 2.3m oz of silver. Paramount is responsible for its legacy reclamation, backed by a $4m surety bond posted through an insurance policy that runs to 2033 and covers reclamation costs up to $25m in aggregate — which is why management expects Sleeper reclamation spending to be reimbursed by insurance rather than funded from cash.
In April 2026 Paramount commissioned an Initial Assessment (SLR International, effective April 29, 2026) and announced results in June. The concept: reprocess the mineralized material already sitting on surface from the Amax era, then open-pit mine in-situ oxide and mixed material, running roughly 33,000 short tons/day through crush-agglomerate heap leaching with Merrill-Crowe recovery.
| Sleeper Initial Assessment (base case) | Figure |
|---|---|
| Gold price / silver price assumption | $3,600/oz / $48/oz |
| Mine life | 17 years |
| Recovered gold (life of mine) | 1,101,000 oz (avg. 65,000 oz/yr) |
| Recovered silver (life of mine) | 3,376,000 oz (avg. 199,000 oz/yr) |
| Gold recovery rate | 75.8% |
| Total average operating cost | $11.82 per short ton stacked |
| Cash costs / AISC, net of by-products | $2,048/oz Au / $2,407/oz Au |
| Initial capital | $201m |
| Sustaining capital / closure | $343m / $52m |
| Post-tax NPV at 8% / IRR / payback | $402m / 44.5% / 1.4 years |
| Pre-tax NPV at 8% / IRR / payback | $505m / 51.3% / 1.3 years |
Three things to hold in mind before taking that $402m at face value.
An Initial Assessment is the lowest-confidence economic study the SEC recognizes. The filing states it plainly: it exists to support disclosure of mineral resources, it is preliminary, and under SEC guidelines it cannot support disclosure of mineral reserves. Grassy Mountain has reserves; Sleeper does not. The two projects' numbers are not comparable in confidence, even though both tables look alike.
The cost profile is front-loaded in Paramount's favour in a way that does not persist. All-in sustaining cost of $2,407/oz is far above Grassy Mountain's $1,442/oz, and even that flattered figure comes with the filing's own warning: it "reflects the benefit of low-cost ounces already stacked on the existing heap leach pads, which require minimal additional spending to recover. As these legacy ounces are depleted and replaced with newly mined material, unit costs are expected to gradually normalize toward long-term levels." Sleeper is also unusually capital-hungry over its life — $343m of sustaining capital against $201m of initial capital, meaning the project consumes roughly $544m of capital in total to produce 1.1m oz.
One figure in the filed table does not reconcile. The Initial Assessment lists total leach feed of 193,000 thousand short tons (193m tons) at a gold leach head grade of 0.08 oz/ton. At 75.8% recovery that would yield roughly 11.7m oz, more than ten times the 1,101,000 oz the same table reports as recovered. The silver line reconciles correctly against 193m tons, which points to the gold grade being misprinted by a factor of about ten — the internally consistent figure is closer to 0.0075 oz/ton, a grade appropriate to heap-leaching old dump material. This does not change the economics the study reports, but it is a reason to read the recovered-ounce and capital figures as the authoritative ones and treat the grade line as a typographical error rather than data.
Sulfide resources are excluded from the mine plan entirely and are flagged as a possible future opportunity requiring more work. The Initial Assessment recommends a $8.5m advancement program — resource-confidence drilling, metallurgical and geotechnical studies, environmental baseline work, permitting support and heap-leach engineering — to carry Sleeper toward a pre-feasibility study. Sleeper's net book value at June 30, 2026 was approximately $25.6m.
Cash runway and the going-concern warning
The auditors' and management's conclusion is unchanged and unambiguous: there is substantial doubt about the company's ability to continue as a going concern for the twelve months after the financial statements were issued. That phrase is a formal accounting determination, not a prediction of failure — it means the company cannot demonstrate, from resources already committed, that it can meet its obligations for a year without raising more money.
Management states that existing cash resources fund operations "through approximately March 2027" — about nine months from the balance sheet date, and roughly six months from the filing date. The FY2027 budget explains why $9.93m does not stretch further:
| FY2027 planned spending | Amount | Nature |
|---|---|---|
| Corporate costs, completion of Grassy permitting, claim maintenance, general expenses | $5.7m | Non-discretionary |
| Water wells for Grassy Mountain mine production and monitoring | $1.1m | Discretionary |
| Drilling the historic Sleeper heap leach pads | $1.6m | Discretionary |
| Long-lead materials and initiation of Grassy Mountain power line | $2.5m | Discretionary |
| Total if fully executed | $10.9m | — |
Note what has changed in character here. The $2.5m power line procurement and the $1.1m of production water wells are not exploration — they are early construction spending. Paramount is starting to pre-position for building a mine while explicitly labelling that spending discretionary and "subject to available cash on hand and additional share issuances." Elsewhere the 10-K puts its next-twelve-month exploration and development budget at "approximately up to $2.7 million," which sits below the $5.2m of discretionary items listed above — the practical reading is that these are ranked options to be funded as cash allows, not a committed program.
Stated funding sources for FY2027 are the existing cash, continued ATM issuance, insurance proceeds for Sleeper reclamation, and further equity financings or royalty sales. Since 2015 the company has funded itself through exactly this mix. Subsequent to June 30, 2026 it had sold a further 91,000 ATM shares for $128,130 net — about $1.41 per share, consistent with the tap staying open but not being pulled hard.
Forward read
What management says it will do: finish Oregon state permitting at Grassy Mountain, keep claims in good standing, fund $5.7m of non-discretionary corporate and permitting costs, and execute up to $5.2m of discretionary project work if cash allows, drawing on the ATM, insurance recoveries and possible royalty sales. It expects to keep paying debenture interest in shares rather than cash.
What that implies but does not say: the next financing is not optional, and its size and form are the whole investment case from here. Paramount enters FY2027 with $9.93m against $10.9m of identified spending and a stated runway ending around March 2027. It will be back in the market — and its own recent history shows how much the terms depend on the share price at that moment. The FY2025 ATM cleared at roughly $0.50 net per share and raised $2.36m; the FY2026 ATM cleared at roughly $1.58 and raised $13.91m. Same facility, same mechanics, entirely different outcome for existing holders.
What to watch, in order of how much it moves the company:
- Final Oregon state permits at Grassy Mountain. The federal Record of Decision is signed and the draft consolidated permit package has been through public consultation; the remaining step is issuance of final state permits. That is the last regulatory gate before Grassy Mountain is a fully permitted, reserve-backed, feasibility-stage project — a materially different asset to finance or sell than a project awaiting approval.
- How the $189.8m is funded. Paramount's stated strategy is explicitly to sell projects, joint venture them, or build small mines itself. Sprott already holds a right of first refusal over any stream, royalty or similar interest Paramount tries to sell, which constrains the cheapest non-dilutive route. Watch for a strategic partner, a construction financing package, or an outright sale — and watch whether the pre-existing royalty load (Sprott's prospective 4.75% gross revenue royalty plus third-party net smelter returns) narrows the field of counterparties.
- Whether Sleeper gets funded past the study stage. The $8.5m advancement program toward a pre-feasibility study is not in the FY2027 budget; only $1.6m of heap-pad drilling is. On current plans Sleeper stays a resource-stage asset with an Initial Assessment attached, and its $402m post-tax NPV stays a modelled figure rather than a financeable one.
- The gold price. Both studies assume $3,600/oz. Grassy Mountain has enough margin at a $1,442/oz all-in sustaining cost to absorb a meaningful pullback; Sleeper, at $2,407/oz and with the filing's own caveat that unit costs normalize upward as legacy stacked ounces deplete, has considerably less room.
Our view. FY2026 was a genuinely good year executed in the right sequence: the company used a metals-price-driven re-rating in its own stock to refill the treasury before it needed to, rather than issuing into weakness as it did in FY2025, and it spent the proceeds on the two things that create optionality — federal approval at Grassy Mountain and a first economic study at Sleeper. The reported $15.56m loss overstates what went wrong, since 37% of it is non-cash marks that rose precisely because gold and the share price rose.
The unresolved problem is one that a good year does not fix. A 38.9% post-tax internal rate of return on a $189.8m build is only worth what someone will pay to fund it, and Paramount has $9.93m, a going-concern qualification, a March 2027 runway on its own estimate, and a secured lender holding both a right of first refusal over royalty sales and deeds of trust over both properties. The company has moved from "will this project ever be permitted" to "who pays for it and on what terms" — real progress, and a question it cannot answer alone.